9/30/25
Water main replacement work will continue on Wednesday, October 1. We do not anticipate any service interruptions.
Final paving, sidewalk and driveway repairs will be completed at the end of entire project.
While we improve your service lines, check out our improved customer service tool, AquaHawk.
See hourly water use, set use alerts, and control your water use at MAWSA.AquaHawk.us.
Use your billing statement account number and service ID number to register. No email? Reach out to our office team and we will help you register without one.
09/22/2025 5PM
With work remaining in the Ferdinand Street area, it is possible to experience intermittent water outages Tuesday and Wednesday of this week (9/23 and 9/24). This is NOT expected, but as we saw earlier in the project we had some unexpected outages due to inoperable valves or unexpected connections beneath the street. To minimize any inconvenience during this time, it would be advisable to have an extra few gallons on hand in pinch in the event service goes down. Plan is to work from Grant back east along Ferdinand, completing near Pitt or Charlotte tomorrow, Wednesday continuing north towards Main Street. Residents along Ferdinand who received the new service connections likely would not experience the issue, rather those customers on the outer edges may notice this.
Restoration of sidewalk damage and full mill and paving repairs for the street will commence upon the completion of the project.
9/19/25
The latest on the MAWSA Water Main Replacement and Extension Project looking towards the week of 9/22
- New water main replacement has been completed. Temporary patching of area at Main called out by PennDOT completed.
- Approximately half of new services have been run (basically between Main and Charlotte), remaining will be completed by Wednesday of next week, with final tie-ins wrapping up the week of 9/29.
- There is no anticipated service disruption other than brief outage at each residence while the new connection is being made.
- Restoration of sidewalk and full mill and paving repairs will commence upon the completion of the project.
9/15/25
Service Line connections will continue Monday and likely through Wednesday or Thursday. Parking restrictions still in effect, but the crews are making progress moving west.
9/5/25
Work will resume Wednesday 9/10 to make service line connections starting at Main Street and working westward. This is expected to take about 4-5 days to get the whole way to Grant Street. We apologize for the inconvenience, but this is an important effort to replace aging infrastructure.
8/29/25
First section of water main replacement wrapped up this week (Main Street to Charlotte Street). Starting Tuesday, work will continue from Charlotte Street to Grant Street. Service connections begin the week of September 9th.