9/19/25
The latest on the MAWSA Water Main Replacement and Extension Project looking towards the week of 9/22
- All water main activity along W High Street has been completed and all service connections have been made except for 1 which we will coordinate with the owner
- Bac-T samples are good along the new service line along the private lane at the end of the line across from Hossler Road.
- Once pressure testing is completed, services will be run to the remaining two customers at the lane and there will be work to remove existing meter pit adjacent to the entry to the lane along W High Street. There are no further service disruptions expected except for brief interruption at the home getting new service connections at the time the connection is being switched.
- Temporary patching of rough spot called out by PennDOT
- Final paving and repairs along road and driveways will be completed at the end of entire project
8/29/25
New water main running back the private lane across from Hossler Road will be connected, hooked up and tested. Service lines to customers along the lane will be installed in the week of September 9th.