2022 Meter Replacement Project

All meters are being replaced in 11 phases to a Sensus brand meter and transmitter. Phase 1 started scheduling the week of October 24 with a MAWSA authorized contractor. It is anticipated that the project will run through Spring of 2023. ** (Phase 11 opened in January 2023.)

**Appointments are being scheduled by the contractor Tuesday through Saturday, 8AM to 4PM. Please refer to the message box on your monthly billing statement for project details. Replacement is mandatory. ** As of January 19, 2023 the project is in a temporary hold while we await delivery of ordered equipment. Once received installations will resume. **

We will revise this project update page as we move forward.

PROJECT TASKCURRENT STATUS
Secure contractsCompleted
Obtain & install base stationCompleted
Install and integrate softwareIn progress
Install Test Meters and transmitters (1 of 2)Completed
Install Test meters and transmitters (2 of 2)Completed
System integration testingIn progress
Phase 1 meter and/or transmitter installationsIn progress
Phase 2 meter and/or transmitter installationsIn progress
Phase 3 meter and/or transmitter installationsIn progress
Phase 4 meter and/or transmitter installationsIn progress
Phase 5 meter and/or transmitter installationsIn progress
Phase 6 meter and/or transmitter installationsIn progress
Phase 7 meter and/or transmitter installationsIn progress
Phase 8 meter and/or transmitter installationsIn progress
Phase 9 meter and/or transmitter installationsIn progress
Phase 10 meter and/or transmitter installationsIn progress
Phase 11 meter and/or transmitter installationsIn progress
Please keep an eye on the message box on your monthly billing statement for details regarding the meter replacement project.